Activity is temporary and limited. The noise derives from the rig engines within the site, the rotary equipment of the rig and from the transiting vehicles (cars and trucks). The level of noise will be monitored at the site fence and other nearby structures.
The rig site preparation will take between 6 to 7 weeks. Any disturbance generated by the construction activity will be temporary and limited. Specific conditions of the surrounding areas will be considered to further minimize the impact. Well drilling activity will take circa 5 to 6 weeks and at the end of the drilling operations, if the well will not be successful, the site will be restored to its original conditions in 6 to 7 weeks.
During site construction, the level of noise should not exceed 80-
In the site, there will be no buildings or concrete visible constructions. The only visible structure while drilling will be the rig tower (mast), which has a visual impact similar to one electric trellis.